In the basement

saw
Saw by s2photography
Originally uploaded by Big Dadoo.

This weekend the renovations focused mainly on the basement.

During the week Eric & Dez finished the upstairs drywall and started mudding the walls. Currently there are a couple of coats in most areas and sanding should start during the week.

On the weekend about 3/4 of the exterior basement walls have been studded and the utility room framed up. The perimeter wiring is in place and some insulation and vapor barrier is up on some walls.

Several bits of plumbing have been capped off or moved, and some of the reconnections are proving to be a challenge. About eight 8′ lengths of framing for enclosing the heating ducts were assembled and are ready to attach to the joists. So, quite a bit of progress in the basement and it’s starting to look quite good.